Duration:
6 Weeks
Value:
Circa £170k
Concept, design & commissioning
The adjacent business car park is routinely under capacity and therefore the proposal was to rebalance the demand with…
The adjacent business car park is routinely under capacity and therefore the proposal was to rebalance the demand with capacity and seek to improve both the revenue stream and customer service within the car park.
Inviron Limited was awarded this project as part of their undertaking as a Local Project Integrator (LPI) for HAL, and as such were appointed as the Principal Contractor to oversee the design and installation of the associated works.
Gatwick Construction Limited (GCL) was the preferred contractor to undertake the building and civil engineering aspects of the project for Inviron, due to our ability to mobilise at short notice and our commitment to deliver the project on schedule. The scope of work included for:
Planning the sequence of works was fundamental to the success of this project, as the car park had to remain open for the duration of the work. Furthermore, the work had to be completed in a short period of time prior to the commencement of the holiday season, the busiest period of the year for the car park.
GCL was able to deliver the project ahead of schedule through detailed planning and sequencing of works, in conjunction with strong stakeholder management, keeping disruption to a minimum.
Duration: 6 Weeks
Value: Circa £170k
Concept, design & commissioning
The adjacent business car park is routinely under capacity and therefore the proposal was to rebalance the demand with…
The adjacent business car park is routinely under capacity and therefore the proposal was to rebalance the demand with capacity and seek to improve both the revenue stream and customer service within the car park.
Inviron Limited was awarded this project as part of their undertaking as a Local Project Integrator (LPI) for HAL, and as such were appointed as the Principal Contractor to oversee the design and installation of the associated works.
Gatwick Construction Limited (GCL) was the preferred contractor to undertake the building and civil engineering aspects of the project for Inviron, due to our ability to mobilise at short notice and our commitment to deliver the project on schedule. The scope of work included for:
Planning the sequence of works was fundamental to the success of this project, as the car park had to remain open for the duration of the work. Furthermore, the work had to be completed in a short period of time prior to the commencement of the holiday season, the busiest period of the year for the car park.
GCL was able to deliver the project ahead of schedule through detailed planning and sequencing of works, in conjunction with strong stakeholder management, keeping disruption to a minimum.